At Earthwright, efficiency is key. We streamline our building processes to minimize time without compromising quality, ensuring that every step from design to delivery is optimized for performance and precision.
The result? Our Shelters are built in under 2 months!
Our Building Process
01
Documentation
Generate Specification and Design Documents. We create all detailed documents based on customer selections to guide the construction process.
02
Assemble Modular Floor Sections
We construct the floor sections and install necessary plumbing drains.
03
Install Framed and Insulated Wall and Roof Panels
Then we securely place and seal structural insulated panels to prepare for the walls and roof.
04
Layout and Framing Interior Walls
Arrange and construct interior walls according to the design plan.
05
Install and Seal Windows and Doors
Fit and seal windows and doors to ensure weather-tightness and insulation.
06
Utility Set-up
We carefully install Mechanical, Electrical, and Plumbing Rough-ins. Laying the groundwork for essential systems within the structure.
07
Exterior Finishings
Complete Exterior Siding, Trim, Soffit, and Fixture Installations. Finish the outer aesthetic and functional elements of the home.
08
Interior Finishing
We apply final touches like drywall, paint, cabinets, flooring, doors, and trim.
09
Utility Quality Assuance
we test all Mechanical, Electrical, and Plumbing Systems, ensuring all systems are properly installed and functioning perfectly.
10
Appliances
Nearing the end of our process, we install Appliances and Window Coverings.
11
Final Quality Assurance
Before preparing for installation, we always conduct a thorough inspection and quality check before the home leaves the factory.
12
Prep for Transport
Securely package the modular home and load it for transportation to the site.